← Business And Income Project · source: files/launch-plan-to-2027-01-01.md
Launch Plan — backward from January 1, 2027
Built 2026-11-25 (night) from the target launch date in Dun's Social Media Marketing Master Brief. Status: PLAN ONLY. Nothing here is scheduled or built until Dun approves the sequence. "Launch" in Dun's standing definition = READINESS: everything working and verified the day he says go. Here the date is fixed, so readiness must be complete by Dec 31, 2026.
What "launched" means on Jan 1, 2027
- dunchau.com live in full (out of splash mode): three services — 1 AI Visibility, 2 Business Efficiency, 3 Business Growth — with published pricing.
- The AI Visibility Playbook published openly on the site; the free personalized summary is the gated step, wired end-to-end (form → delivery → booking).
- CRM live: engagement-based lead scoring, self-booking appointments, follow-up sequences with conversion tracking.
- dun@dunchau.com working as the public contact email (site, cards, profiles).
- Social profiles consistent on all five platforms, content cadence running from a pre-drafted bank.
- Every flow TESTED with a verified landing (the Payas lesson: nothing counts as working until its arrival is confirmed).
The five weeks
Week 1 — Nov 25–29 · Thanksgiving (family first) - Dun's only actions: the approved pizzeria comment (Wed Nov 25) and any posts he chooses. No decisions asked. - Background build: Playbook v2 rewrite from the SMB filter (41-element verdict table already done).
Week 2 — Nov 30–Dec 6 · Decisions week (the gates) - AIGP ruling (daily reminder starts Mon Nov 30 unless Dun re-decides — the certification was Risk Shield credibility; keep, repurpose, or cancel). - CRM selection: GoHighLevel is the researched default from the growth report. One decision unlocks Phase 3. - Email host approval for dun@dunchau.com (Google Workspace ~$7/user/mo is the standard route; not yet approved). - Password resets/updates for Instagram and X (one careful attempt each with the correct username — thedunchau — to avoid lockouts), then the pending bio edits complete the five-platform set. - Run 3 carousel: approve or hold.
Week 3 — Dec 7–13 · Build the machine - CRM setup: pipelines for the three services, lead-scoring rules (playbook download, summary request, pricing visit, booking), self-booking calendar for the 30-minute call, follow-up sequences — short, fixed, no artificial urgency, per the V3 philosophy. - Mailboxes live: dun@, info@, support@ on the chosen host; MX via Cloudflare; form-alert recipient flips to info@. - Playbook landing page staged into the site build; free-summary request flow wired to the CRM.
Week 4 — Dec 14–20 · Site and profiles - Full site deployed out of splash mode with the staged V3 batch: service #3 swap, theme-ordered subline, playbook page, support page. - Public email swapped to dun@dunchau.com on site, business card, and profiles. - Note: Holiday Matsuri runs Dec 18–20 — badge decision deadline is Dec 1 (Week 2).
Week 5 — Dec 21–27 · Content bank (Christmas week, light) - Two weeks of platform-adapted posts drafted under the Master Brief (40% home services / 35% professional & legal / 25% B2B commercial; Central Florida angle), each drafted per platform, none published without approval. - The 60-second Efficiency video recorded from the approved script. - Industry editions of the playbook (law, dental, home services) drafted from the master.
Final days — Dec 28–31 · Verify, then launch - End-to-end tests: playbook download, summary request (confirm the alert lands), booking (confirm the calendar event and the CRM record), follow-up sequence fires once, correctly. - Jan 1, 2027: launch. First-week watch: every inbound item confirmed by hand until the machine has a track record.
Decision gates (Dun's, in order)
- AIGP — keep / repurpose / cancel (by Nov 30).
- CRM — GoHighLevel or alternative (Week 2).
- Email host — approve spend (Week 2).
- Holiday Matsuri badge (by Dec 1).
- Site release out of splash mode (Week 4, on the staged batch).
- Run 3 carousel and the content bank (approve drafts, Weeks 2 and 5).
Honest constraints
- Two holiday weeks sit inside this window; the plan already treats them as light. Slippage lands on the content bank first, never on the Week 3 machine build — a launch without the CRM and booking working is a splash page with better graphics.
- The three blocked profile bios do not block launch; LinkedIn and Facebook (the two that matter most for this buyer) are already updated and verified.